Category : Press Release
Date : April 12, 2019
Agency : Public-Private Partnership Center
Title : PPP Project Update: Clark International Airport Expansion Project
Article : As of March 2019, the Clark International Airport Expansion Project is 52% complete. This was announced by Bases Conversion and Development Authority (BCDA) President Vince Dizon during the site inspection conducted on March 27, 2019. The project involves the construction of a new 93,000 sq. m. Passenger Terminal Building, with a design capacity of 8 million passengers per annum. The construction is expected to be completed by mid-2020.‚Äč
Link : https://ppp.gov.ph/press_releases/ppp-project-update-clark-international-airport-expansion-project/